9.8.10. Cantilevered Precast Concrete Steps

9.8.10. Cantilevered Precast Concrete Steps
9.8.10.1. Design
  1. Exterior concrete steps and their anchorage system that are cantilevered from a foundation wall shall be designed and installed to support the loads to which they may be subjected.
9.8.10.2. Anchorage
  1. Cantilevered concrete steps referred to in Article 9.8.10.1. shall be anchored to concrete foundation walls not less than 200 mm thick.
9.8.10.3. Prevention of Damage Due to Frost
  1. Suitable precautions shall be taken during backfilling and grading operations to ensure that subsequent freezing of the soil will not cause uplift forces on the underside of cantilevered concrete steps to the extent that the steps or the walls to which they are attached will be damaged.