9.12.1. General

9.12.1. General
9.12.1.1. Removal of Topsoil and Organic Matter
  1. The topsoil and vegetable matter in all unexcavated areas under a building shall be removed.
  2. In localities where termite infestation is known to be a problem, all stumps, roots and other wood debris shall be removed from the soil to a depth of not less than 300 mm in unexcavated areas under a building.
  3. The bottom of every excavation shall be free of all organic material.
9.12.1.2. Standing Water
  1. Excavations shall be kept free of standing water.
9.12.1.3. Protection from Freezing
  1. The bottom of excavations shall be kept from freezing throughout the entire construction period.