9.20.4.2. |
Masonry Units
- Hollow masonry units shall be laid with mortar applied to head and bed joints of both inner and outer face shells.
- Vertically aligned webs of hollow masonry units shall be laid in a full bed of mortar
- under the starting course,
- in all courses of columns, and
- where adjacent to cells or cavities that are to be filled with grout.
- Except for head joints left open for weep holes and ventilation, solid masonry units shall be laid with full head and bed joints.
|