9.23.7.2. |
Levelling and Sealing of Sill Plates
- Sill plates shall be
- levelled by setting them on a full bed of mortar, or
- laid directly on the foundation if the top of the foundation is level. (See also Article 9.23.2.3.)
- 2) The joint between the sill plate for exterior walls and the foundation shall be sealed in accordance with Subsection 9.25.3.
|