Headers

Photo Source: Summerhill
Photo Source: Summerhill




Photo Source: Summerhill



Ensure:

  • Adequate depth for the required R-value
  • Adequate access is available for installing insulation
  • Floor joists and rim joists are free of rot or other damage
  • Any installed duct work will not prevent the installation of insulation

Note: